Ditton Road, Widnes

 

Project Value: c£1m

Client/Contractor: Fallon Brothers

Start/End Date: November 2012 – October 2013

This industrial site was being re-developed for use as a new metal recycling, vehicle storage and depolluting facility.

The site was located in an area where significant thicknesses of chemical waste (Galligu) had been historically deposited. Initial services included detailed geo-environmental risk assessment to satisfy local authority and Environment Agency requirements and design of external areas to mitigate against ground settlement.

Subsequent services involved application for an Environmental Permit and subsequent preparation of an Environmental management System. Significant cost savings were provided by diverting contaminated waste water to foul sewer under Temporary Discharge Consent.

 

 

 

 

 

 

 

 